We work with Alstal
NMG S.A. signed a contract with ALSTAL for the supply and implementation of a building management system in an expanded hospital in Gniezno.
In the first stage, building D will be put into operation, in which, among others, operating rooms with all the necessary technical facilities are located. As part of the contracted works, NMG will provide a BMS based on its own ERCO.Net software. The complete solution will be responsible, among others, for:
• automation of air handling units, including central control rooms for operating rooms
• control of roof fan sets
• operation control of VAV systems
• air conditioning regulation in 285 rooms
• monitoring of electrical switchboards
• monitoring of the generator set
• monitoring of elevators